Bulgaria's HPP Chaira extends unplanned outage of unit

Bulgaria's HPP Chaira extends unplanned outage of unit Lower reservoir Chaira Dam and entrance to PSHPP Chaira / Photo: NEK

Bulgarian pumped-storage hydro power plant (HPP) Chaira has extended the unplanned outage of one of its units by three days to August 23, the Independent Bulgarian Energy Exchange (IBEX) said on Tuesday.

HPP Chaira shut down one of its units on August 10 for unplanned restoration works, which was expected to resume operations on August 20, IBEX data shows.

While the works take place, the plant will be left with 216 MW of unavailable generating capacity and 198 MW of pumping mode capacity.

HPP Chaira, which is the biggest pump-storage hydro power plant in Southeast Europe according to its state-owned operator NEK, has an installed capacity of 864 MW in generating mode and 792 MW in pumping mode.

Choose your newsletter by Renewables Now. Join for free!

More stories to explore
Share this story
Tags
 
About the author
5 / 5 free articles left this month
Get 5 more for free Sign up for Basic subscription
Get full access Sign up for Premium subscription