OX2 taps CJR Renewables to build 99.2-MW wind farm in Romania
Sep 18, 2024 15:06 CESTThe European Bank for Reconstruction and Development (EBRD) said on Tuesday it will provide a senior loan of 49 million euro ($67.4 million) for the construction of a 108 megawatts (MW) wind farm in Romania.
Parallel to EBRD's funding, Austria's Erste Group will contribute 49 million euro, while Erste's Romanian subsidiary Banca Comerciala Romana (BCR) will provide a 27 million euro value added tax funding loan facility, EBRD said in a statement.
Crucea North wind farm, located in the southeastern Dobrogea region, is owned by German power producer STEAG GmbH and will comprise 36 turbines. The total cost of the project is expected to be approximately 200 million euro.
Preliminary construction works at the wind park began late last year and are scheduled to be completed by mid-2015.
The project is expected to reduce CO2 emissions by 140,000 tonnes per year.
($=0.7266 euro)
OX2 taps CJR Renewables to build 99.2-MW wind farm in Romania
Sep 18, 2024 15:06 CESTRomania opens inaugural 1.5-GW CfD renewables auction
Sep 12, 2024 12:17 CESTEngie Romania unveils 57-MW wind, solar hybrid
Sep 04, 2024 16:34 CESTRomania's CIS Group to build 23-MW solar park at home
Sep 19, 2024 9:59 CESTRomania's Electrica bags funds for 69.9-MWh battery project
Sep 18, 2024 8:52 CESTPhoton Energy brings live 7.5-MWp solar park in Romania
Sep 17, 2024 7:41 CEST