Minesto to resume Faroe Islands tidal kite commissioning in mid-October

Minesto to resume Faroe Islands tidal kite commissioning in mid-October The DG500 kite. Source: Minesto AB

Swedish marine energy developer Minesto AB intends to continue with the commissioning of its tidal power array in Vestmannasund, Faroe Islands in mid-October.

Earlier this summer, the company successfully connected the offshore site of its Faroe Islands project to the grid, but failed to commission the first DG100 tidal kite device there because of a mechanical failure in the mooring interface. According to CEO Martin Edlund, the repair will take a few more weeks to complete.

“We have generated valuable flight data and control system data, and we have verified the chain of electricity distribution to shore. The marine operations, with towing and installation, went as planned which is also very good,” Edlund said.

Meanwhile, Minesto has carried out measurements of tidal flow conditions in another part of the Faroe Islands. Together with Faroese electric utility SEV, the company has verified the location for the first large-scale project on the islands, Edlund added.

Choose your newsletter by Renewables Now. Join for free!

More stories to explore
Share this story
Tags
 
About the author
Browse all articles from Ivan Shumkov

Ivan is the mergers and acquisitions expert in Renewables Now with a passion for big deals and ambitious capacity plans.

More articles by the author
5 / 5 free articles left this month
Get 5 more for free Sign up for Basic subscription
Get full access Sign up for Premium subscription